@@ -18,7 +18,7 @@ Independent tasks are run in order of creation time, earliest first. Tasks with
## Dependency Manager
Responsible for looking at each pending task and determining whether it should create a dependency for that task.
For example, if `update_on_launch` is enabled of a task, a project update will be created as a dependency of that task. The Dependency Manager is responsible for creating that project update.
For example, if `scm_update_on_launch` is enabled for the project a task uses, a project update will be created as a dependency of that task. The Dependency Manager is responsible for creating that project update.
Dependencies can also have their own dependencies, for example,
@@ -47,17 +47,17 @@ Dependencies can also have their own dependencies, for example,
### Dependency Manager Steps
1. Get pending tasks (parent tasks) that have `dependencies_processed = False`
2. Create project update if
2. As optimization, cache related projects and inventory sources
3. Create project or inventory update for related project or inventory source if
a. not already created
b. last project update outside of cache timeout window
3. Create inventory source update if
a. not already created
b. last inventory source update outside of cache timeout window
4. Check and create dependencies for these newly created dependencies
a. inventory source updates can have a project update dependency
5. All dependencies are linked to the parent task via the `dependent_jobs` field
b. last update failed
c. last project update outside of cache timeout window
d. some extra logic applies to inventory update creation
4. All dependencies (new or old) are linked to the parent task via the `dependent_jobs` field
a. This allows us to cancel the parent task if the dependency fails or is canceled
6. Update the parent tasks with `dependencies_processed = True`
5. Update the parent tasks with `dependencies_processed = True`
6. Check and create dependencies for these newly created dependencies
a. inventory source updates can have a project update dependency
## Task Manager
@@ -110,7 +110,7 @@ Special note -- the workflow manager is not scheduled to run periodically *direc
Empirically, the periodic task manager has been effective in the past and will continue to be relied upon with the added event-triggered `schedule()`.
### Bulk Reschedule
### Bulk Reschedule
Typically, each manager runs asynchronously via the dispatcher system. Dispatcher tasks take resources, so it is important to not schedule tasks unnecessarily. We also need a mechanism to run the manager *after* an atomic transaction block.